Lower Junction Construction Update

West Towns – 20 Perth Avenue

Drilling is scheduled to be completed by Friday, May 5th, weather permitting. The drill rig is scheduled to be removed from the site no later than Monday, May 8th; though weather conditions may cause this scheduled to be revised.

The week of May 8th will see site clean up and initial excavation work commence.

Excavation includes soil removal and the digging of trenches between the steel poles that have been placed on the east and west perimeter of the site. The trenches are filled with lagging - wooden beams - that complete the shoring.

 

Auto Building – 158 Sterling Road

Restoration work continues on the historic Auto Building with electrical and plumbing systems being installed throughout the building. Almost all the new windows have been installed with the remainder to be fitted into place in the next few weeks.

Work continues in the basement to install the key components of the electrical, HVAC and plumbing systems. Heating and cooling equipment has begun to arrive onsite and will be installed in the coming weeks.

Notes:

Construction hours on the site will be in accordance with the City of Toronto Construction Noise by-law [Toronto Municipal Code Noise § 591-2.1] with work occurring Monday to Friday between 7 am and 7 pm, and if required between 9 am and 7 pm on Saturdays

Castlepoint Greybrook Sterling Inc. has provided an alternative to street parking for residents on Perth Avenue. A portion of the land at the corner of Perth Avenue and Sterling Road has been made available for those with parking passes.