Lower Junction Construction Update

West Towns – 20 Perth Avenue

The next phase of work on the West Towns site is underway. Shoring the perimeter of the site has started, which will be followed by excavation work shortly after.

To begin the shoring process, holes will be drilled then steel I-beams will be placed in position. A drill rig arrived on site on April 20th. Drilling is expected to continue through the coming week. Vibration levels will be monitored and kept within permitted limits. 

Construction hours on the site will be in accordance with the City of Toronto Construction Noise by-law [Toronto Municipal Code Noise § 591-2.1] with work occurring Monday to Friday between 7 am and 7 pm. If required, additional work is permitted to take place between 9 am and 7 pm on Saturdays. 

A reminder on parking: 

Castlepoint Greybrook Sterling Inc. (CGSI) has provided an alternative to street parking for residents on Perth Avenue. A portion of the land at the corner of Perth Avenue and Sterling Road has been made available for those with parking passes. 

  • If you live on Perth Avenue and wish to have a parking pass please contact Philip Share or Brett Rycombel, Co-Chairs of the South Perth And Sterling Road Residents Association. Philip Share may be contacted at 416-706-2469.